Docsity
Docsity

Prepare for your exams
Prepare for your exams

Study with the several resources on Docsity


Earn points to download
Earn points to download

Earn points by helping other students or get them with a premium plan


Guidelines and tips
Guidelines and tips

Professional Scrum Master I (PSM I) Questions And Answers, Exams of Computer Science

Professional Scrum Master I (PSM I) Questions And Answers

Typology: Exams

2024/2025

Available from 07/14/2025

Nurseexpert
Nurseexpert 🇺🇸

4.7

(3)

4.8K documents

1 / 16

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
Professional Scrum Master I (PSM I)
Questions And Answers
How much work must a Development Team do to a Product Backlog
item it selects for a Sprint? -
correct answer As much as it has told the Product Owner will be
done for every Product Backlog item it selects in conformance with
the definition of "Done".
*Reason:* The purpose of each Sprint is to deliver Increments of
potentially releasable functionality that adhere to the Scrum Team's
current definition of "Done".
*True or False:* The Scrum Team should choose at least one high
priority process improvement, identified during the Sprint
Retrospective, and place it in the Product Backlog. -
correct answer False
*Reason:* To ensure continuous improvement, the Sprint Backlog
rather than the Product Backlog includes at least one high priority
process improvement identified in the previous Sprint
Retrospective meeting.
pf3
pf4
pf5
pf8
pf9
pfa
pfd
pfe
pff

Partial preview of the text

Download Professional Scrum Master I (PSM I) Questions And Answers and more Exams Computer Science in PDF only on Docsity!

Questions And Answers

How much work must a Development Team do to a Product Backlog item it selects for a Sprint? - correct answer ✅As much as it has told the Product Owner will be done for every Product Backlog item it selects in conformance with the definition of "Done". Reason: The purpose of each Sprint is to deliver Increments of potentially releasable functionality that adhere to the Scrum Team's current definition of "Done". True or False: The Scrum Team should choose at least one high priority process improvement, identified during the Sprint Retrospective, and place it in the Product Backlog. - correct answer ✅False Reason: To ensure continuous improvement, the Sprint Backlog rather than the Product Backlog includes at least one high priority process improvement identified in the previous Sprint Retrospective meeting.

Questions And Answers

True or False: When multiple teams work together on the same product, each team should maintain a separate Product Backlog. - correct answer ✅False Reason: Products have one Product Backlog, regardless of how many teams are used. Any other setup makes it difficult for the Development Team to determine what it should work on. Who is responsible for managing the progress of work during a Sprint? - correct answer ✅The Development Team Reason: The Development Team uses the Daily Scrum to inspect progress toward the Sprint Goal and to inspect how progress is trending toward completing the work in the Sprint Backlog. True or False: It is mandatory that the product increment be released to production at the end of each Sprint. - correct answer ✅False Reason: The product increment should be usable and releasable at the end of every Sprint, but it does not have to be released.

Questions And Answers

Master or Product Owner is also on the Development Team, they will need to be at the Daily Scrum. Otherwise, the Scrum Master simply has to make sure the Development Team knows how to conduct a Daily Scrum and does so. The length of a Sprint should be: - correct answer ✅1) Short enough to keep the business risk acceptable to the Product Owner.

  1. Short enough to be able to synchronize the development work with other business events.
  2. No more than one month. Which statement best describes Scrum? - correct answer ✅A framework within which complex products in complex environments are developed. Reason: Scrum is not a process or a technique for building products; rather, it is a framework within which you can employ various processes and techniques.

Questions And Answers

Development Team membership should change: - correct answer ✅As needed, while taking into account a short term reduction in productivity. Reason: Teams typically go through some steps before achieving a state of increased performance. Changing membership typically reduces cohesion, affecting performance and productivity in the short term. Who creates the definition of "Done"? - correct answer ✅The development organization (or Development Team if none is available from the development organization) Reason: If the definition of "done" is part of the conventions, standards or guidelines of the development organization, all Scrum Teams must follow it as a minimum. The Development Team of the Scrum Team can complement it with elements specific for the product or context.If "done" for an increment is not a convention of the development organization, the Development Team of the Scrum Team must define a definition of "done" appropriate for the product.

Questions And Answers

During a Sprint, a Development Team determines that it will not be able to finish the complete forecast. Who should be present to review and adjust the Sprint work selected? - correct answer ✅The Product Owner and the Development Team. Reason: During the Sprint, scope may be clarified and re- negotiated between the Product Owner and Development Team as more is learned. Select three incorrect, untrue, or misleading statements about Scrum? - correct answer ✅1) Scrum is like traditional processes but with self- organization to replace Project Managers.

  1. Scrum is a framework that eliminates complexity.
  2. Scrum is a methodology where you can pick and choose which parts of Scrum you think will work for your environment. Reasons: Project Managers are not simply replaced by self- organizing teams. Scrum does not eliminate the complexity that is inherent in delivering a product in today's world, instead it offers a

Questions And Answers

framework for dealing with complexity. The five events in the Scrum Guide are mandatory, as each event has a specific purpose. The maximum length of the Sprint Review (its time-box) is: - correct answer ✅4 hours for a monthly Sprint. For shorter Sprints it is usually shorter. When might a Sprint be abnormally cancelled? - correct answer ✅When the Sprint Goal becomes obsolete. Reason: A Sprint can be cancelled before the Sprint time-box is over, or when the Sprint Goal becomes obsolete. This might occur if the company changes direction or if market or technology conditions change. What is the role of Management in Scrum? - correct answer ✅Support the Product Owner with insights and information into high value product and system capabilities. Support the Scrum Master to cause organizational change that fosters empiricism, self-organization, bottom-up intelligence, and intelligent release of software.

Questions And Answers

  1. The Development Team members are working within the boundaries of their functional description and nicely handing off work from analyst to developer to tester to integration. Reasons: The Daily Scrum is attended by the Development Team and should not be used by external stakeholders to check progress. During Sprint Planning, the Scrum Team crafts the Sprint Goal based on the set of Product Backlog items selected for the sprint. Scrum Development Team members don't have titles, and no sub-teams such as testing, architecture, or operations are recognized. Why is the Daily Scrum held at the same time and same place? - correct answer ✅The consistency reduces complexity. The three pillars of empirical process control are: - correct answer ✅Inspection, Transparency, Adaptation Which of the following services are appropriate for a Scrum Master in regard to the Daily Scrum? - correct answer ✅Teach the Development Team to keep the Daily Scrum within the 15 minute time-box.

Questions And Answers

Which statement best describes the Sprint Review? - correct answer ✅It is when the Scrum Team and stakeholders inspect the outcome of the Sprint and figure out what to do in the upcoming Sprint. Reason: Every event in Scrum, besides the Sprint which is a container for the other events, is an opportunity to Inspect AND Adapt. True or False: Scrum does not have a role called "project manager." - correct answer ✅True Reason: A Scrum Team has a Scrum Master, a Product Owner and a Development Team. As a whole they have all controls needed. True or False: The purpose of a Sprint is to produce a done increment of working product. - correct answer ✅True

Questions And Answers

Reason: Sprint Backlog and all of its items are collectively owned by the Development Team. No individual team member can claim ownership over an item as this would block communication and collaboration. What is the main reason for the Scrum Master to be at the Daily Scrum? - correct answer ✅He or she does not have to be there; he or she only has to ensure the Development Team has a Daily Scrum. The time-box for a Daily Scrum is? - correct answer ✅15 minutes Which statement best describes a Product Owner's responsibility? - correct answer ✅Optimizing the value of the work the Development Team does. The CEO asks the Development Team to add a "very important" item to a Sprint that is in progress. What should the Development Team do? - correct answer ✅Inform the Product Owner so he/she can work with the CEO.

Questions And Answers

Reason: The items selected for a Sprint have been selected as most valuable with the Product Owner. The items serve the Sprint's goal. No changes should be made that endanger the Sprint Goal. No one external to the Scrum Team can force changes on the Development Team (Sprint Backlog) and the Product Owner (Product Backlog). When is a Sprint over? - correct answer ✅When the time-box expires. Reason: The duration of a Sprint is fixed and cannot be shortened or lengthened. Which two things does the Development Team do during the first Sprint? - correct answer ✅1) Deliver an increment of potentially releasable software.

  1. Develop and deliver at least one piece of functionality.

Questions And Answers

Reason: Fewer than 3 Development Team members decreases interaction and results in smaller productivity gains. More than 9 members simply requires too much coordination. An organization has decided to adopt Scrum, but management wants to change the terminology to fit with terminology already used. What will likely happen if this is done? - correct answer ✅1) Management may feel less anxious.

  1. The organization may not understand what has changed with Scrum and the benefits of Scrum may be lost.
  2. Without a new vocabulary as a reminder of the change, very little change may actually happen.