ACQ 202 Module 2 Exam Part II Planning Acquisition Strategy Development EXAM 2024- 2025, Exams of Data Acquisition

ACQ 202 Module 2 Exam Part II Planning Acquisition Strategy Development EXAM 2024- 2025 Using the Standard Capability Maturity Model Integration Appraisal Method for Process Improvement (SCAMPI), an organization whose acquisition processes are well documented and standardized would be rated at least: - ANSWER >>-Level 1 -Level 2 -*Level 3* -Level 4 When selecting a software developer, which of the following should contractors possess (Select all that apply)? - ANSWER >>-*Successful past performance record* -*Domain experience in developing comparable software systems* -Maturity level four -*Demonstrable mature software development capability and processes* With regard to exceptions to the full funding policy, _________ funds are budgeted as a separate procurement line item from the related end item. - ANSWER >>-Multiyear Procurement -Incremental -*Advance Procurement* -Low Rate Initial Production (LRIP)

Typology: Exams

2024/2025

Available from 07/16/2025

jully-shiam
jully-shiam 🇺🇸

847 documents

1 / 4

Toggle sidebar

This page cannot be seen from the preview

Don't miss anything!

bg1
ACQ 202 Module 2 Exam Part II Planning
Acquisition Strategy Development EXAM 2024-
2025
Using the Standard Capability Maturity Model Integration Appraisal Method
for Process Improvement (SCAMPI), an organization whose acquisition
processes are well documented and standardized would be rated at least: -
ANSWER
>>-Level 1
-Level 2
-*Level 3*
-Level 4
When selecting a software developer, which of the following should
contractors possess (Select all that apply)? -
ANSWER
>>-*Successful past
performance record*
-*Domain experience in developing comparable software systems*
-Maturity level four
-*Demonstrable mature software development capability and processes*
With regard to exceptions to the full funding policy, _________ funds are
budgeted as a separate procurement line item from the related end item. -
ANSWER
>>-Multiyear Procurement
-Incremental
-*Advance Procurement*
-Low Rate Initial Production (LRIP)
Earned value management (EVM) reports are available to help the program
manager (PM) track the contractor's cost, schedule, and performance
against a Performance Measurement Baseline. -
ANSWER
>>-*True*
-False
In the Planning, Programming, Budgeting and Execution (PPBE) process,
pf3
pf4

Partial preview of the text

Download ACQ 202 Module 2 Exam Part II Planning Acquisition Strategy Development EXAM 2024- 2025 and more Exams Data Acquisition in PDF only on Docsity!

ACQ 202 Module 2 Exam Part II Planning

Acquisition Strategy Development EXAM 2024-

Using the Standard Capability Maturity Model Integration Appraisal Method for Process Improvement (SCAMPI), an organization whose acquisition processes are well documented and standardized would be rated at least: - ANSWER>>-Level 1

  • Level 2
  • Level 3
  • Level 4 When selecting a software developer, which of the following should contractors possess (Select all that apply)? - ANSWER>>-Successful past performance record
  • Domain experience in developing comparable software systems
  • Maturity level four
  • Demonstrable mature software development capability and processes With regard to exceptions to the full funding policy, _________ funds are budgeted as a separate procurement line item from the related end item. - ANSWER>>-Multiyear Procurement
  • Incremental
  • Advance Procurement
  • Low Rate Initial Production (LRIP) Earned value management (EVM) reports are available to help the program manager (PM) track the contractor's cost, schedule, and performance against a Performance Measurement Baseline. - ANSWER>>-True
  • False In the Planning, Programming, Budgeting and Execution (PPBE) process,

one result of the programming activities is the __________ - ANSWER>>- Future Years Development Program (FYDP)

  • Budget Estimate Submission (BES)
  • Defense Planning Guidance (DPG)
  • Program Objectives Memorandum (POM) If a contractor chooses to use their own quality system, they must demonstrate compliance with the established military standard through formal third party certification. - ANSWER>>-True
  • False The Contracting Officer's responsibilities include all of the following EXCEPT - ANSWER>>-Preparing the request for proposal
  • Managing performance of the contractor on a daily basis
  • Conducting discussions with potential offerors in response to a solicitation
    • Making a modification to an existing contract A _______ is an aggregation of program elements that reflects a macro- level force mission or support mission of DoD. - ANSWER>>-Future Years Defense Program (FYDP)
  • Budget
  • Major Force Program (MFP)
  • Program Objectives Memorandum (POM) If your procurement budget request did not provide for buying a whole number of useable end items, this would be a violation of which funding policy? - ANSWER>>-Annual Funding
  • Full Funding
  • Incremental Funding
  • Deficit Funding Small business set-asides require the expectation that at least three capable small disadvantaged businesses will submit offers. - ANSWER>>- True
  • False

product descriptions (NOT THIS ONE) - modifying the user's requirements

  • proper contract pricing information
  • modifying the available products In a ________ type of contract, the contractor bears virtually all the financial risk associated with procurement. - ANSWER>>-Cost plus incentive fee - Sole source
  • Firm fixed price
  • Cost plus award fee Escalation allows us to make predictions about future costs based on: - ANSWER>>-Expected inflation rates and affordability analyses
  • Expected inflation and outlay rates
  • Expected outlay rates and affordability trade-offs
  • Expected cost/performance trade-offs and affordability analyses